                 Don’t surrender to the cold, build the achievement in the hard environment
                                                                                                                          -
Sidelights on the construction project of Jilin pressure test 
      Snowy Under the Changbai Mountain, Jilin Song source of endless plains, condensed into thick ice near the Songhua River, has a 20-member construction team, to October, has been in the biting winter wind quietly under the stick of their mission. Them, that we in the project department of Jilin Billiton all construction personnel. 
      Jilin pressure test gas pipeline project is a ¢ 711 pressure test drying project. If this project is anywhere in the South construction, this project is not worth mentioning; but this item on the northeastern region of China and the cold season comes, the difficulty of construction project and construction conditions and ordinary people can not bear to imagine. Early October 2008, project managers, led by Tang and strong construction team has been assigned to support the construction site of the Jilin Song source. At that time the climate in the Central Plains area, or fall, but has entered the winter in Jilin. With the expectations of company leaders, with heavy labor supplies, with a deep sense of responsibility, all the staff of Jilin project into the construction of the project without complaint among the ... ... 

     Cold hands cold feet cold ears 
     Twenty or even ten degrees below zero several times, this is a concept? This is a pot of hot water poured on the outside can immediately freezes the scene, this is a do not take reasonable measures to put your ear nose and fingers frozen off the tragedy. However, the face of such a day trip to cold weather, Jilin project construction team retreat and no one is compelling. Some team members who take the initiative in the Northeast live to tell his teammates how to prevent freezing. In this case, we teach each other the experience, but even more solidarity and fraternity. 
      During the excavation pit operation in the pipeline, in order to complete the process as planned, the construction team adhere to the outside more than 10 hours of full operation. Hungry spare biscuits Tiandu Zi, knock the ice to quench their thirst.Operating pit have a certain depth, some operations need to be into the operating pit, and the operating pit are flooded with ice water, some water depth over the knee.Foot in the ice cold water is also more than a knife and cut the pain. In this case, the project manager to work actively take the lead in the pit. Work more than ten degrees below zero, freezing rain that will form a coat of ice, gloves, ice cold adhesive, a little of a move to take off a layer of skin, crack the nuggets out of the neck, with a mass of hot air . A long period of operation, the project manager has stiff hands and feet, limb numbness, unable to stand, fell to the operation of the pit. Rushed to the side of the team met with project managers help to one side off, they would have volunteered to get down to work again. 

      Do their best to maintain 
      Ho and Dong Guan New India is the only driver, but also take up this role of construction machinery and equipment maintenance. In cold conditions, the equipment maintenance is very important. If improper maintenance, not only machinery and equipment not operate normally, and would adversely affect the construction or, worse, would cause all kinds of risks throughout the project. To make equipment to normal operation, any new Indian talents and Dong Guan turns every day maintenance and equipment maintenance, regular inspection, the engine oil. For questions, immediately conduct a study on the problems and solutions, to prevent the occurrence of any hidden dangers. 
      Once the pipe pressure test conducted the day before the procedure, how the new air compressor was found during the test run the air compressor running sound a bit unusual. So this problem immediately reported to the project manager, and call to consult the relevant technical staff headquarters. Jilin wild winter night, a few miles radius there were no infestation, in addition to snow or snow. Before any new construction of a pedestrian in order to ensure the normal operation of the next day, checks and maintenance on the night air compressor in the snow. Hard work pays off, after a full half of the night's efforts, the normal compressor into operation in the next morning in the construction of the. 

      Project quality and quantity of dry 
      Despite how bad the weather conditions, despite the difficulty of how most of the construction of deep, Jilin project construction quality requirements of the construction team, but he is not because of objective conditions and reduce the requirements.Construction period of the day, few people's hands is intact, few people's feet are dry.Snow and ice falling into the shoes can not attend to pour out, tired, no time for more rest. Everyone together, only one goal, that is: quality and quantity required to complete the project. 
      During the pressure test in the pipeline, in order to stabilize the pressure does not leak pressure, one-time finish this process, all the team members actively work to delay the time required to finish this process before going to bed. The bitter wind blowing straight chills all the players, but their underwear and socks are all wet. Cold wind blowing the body, the body is sweating all of a sudden had fallen into through the ice like being inside. But in this situation no one under the bitter shouting, no one Han Lei. 

      Snow still in the gale continued, machinery and equipment still in operation, construction workers are still in the save the snow did not stop moving ... ... the progress of their construction, cold and unyielding at no downed their acoustic shadow. Saw and heard in the Jilin project construction, every detail cry. All project personnel with the interpretation of actions committed to the company the responsibility of the project.

Previous: The project manager who has a high degree of respo
Next: Problems found in Guangdong LNG pipeline construct

  